To be eligible for the PSP certification exam, candidates must have at least five years of experience in the security industry, with at least three of those years in physical security. Candidates must also have a bachelor's degree or equivalent, or have a combination of education and experience that meets the eligibility requirements. Once candidates have met the eligibility requirements, they can register for the exam and begin preparing for the test.
ASIS PSP certification is highly respected in the industry and is recognized by employers worldwide. It demonstrates that the holder has a thorough understanding of the principles and best practices of physical security and can apply them effectively in their work. In addition, certification holders must maintain their credentials through continuing education and recertification, ensuring that they stay up-to-date with the latest developments in the field. Overall, the ASIS PSP certification is an excellent investment for security professionals who want to advance their careers and demonstrate their expertise in physical security.
NEW QUESTION # 49
Constraints control events or activities that __________________.
- A. Are not based on project relationships.
- B. Affect only the forward pass.
- C. Affect only the backward pass.
- D. May be over-ridden by activity logic.
Answer: D
NEW QUESTION # 50
What portion of Activity B is on the critical path?
- A. First half of the activity
- B. None of it
- C. Last half of the activity
- D. The whole activity
Answer: B
NEW QUESTION # 51
Constraints control events or activities that __________________.
- A. Affect only the forward pass.
- B. May be over-ridden by activity logic.
- C. Are not based on project relationships.
- D. Affect only the backward pass.
Answer: C
Explanation:
Role of Constraints:
* Constraints impose specific conditions on schedule events or activities, such as fixed start dates or imposed milestones.
* These are external to the natural logic relationships established in a network (e.g., predecessor- successor relationships).
PSP Study Guide References:
* The guide describes constraints as independent factors that override logic-based sequencing when necessary.
Analysis of Options:
* Option A and C: Constraints impact both forward and backward passes, not exclusively one.
* Option D: Constraints supersede activity logic rather than being overruled by it.
Conclusion: The correct answer is B, as constraints operate independently of project logic relationships.
NEW QUESTION # 52
Who can define KPls?
- A. The client and the performing/contracting entity
- B. The subcontractors and suppliers
- C. Accounting and Finance
- D. Environmental regulators
Answer: A
NEW QUESTION # 53
Communism has common property and radical Islam has sharing property
- A. False
- B. True
Answer: B
NEW QUESTION # 54
In an earned value-based system, a schedule performance index of less than one for the project indicates the project is:
- A. complete
- B. ahead of schedule
- C. behind schedule
- D. on schedule
Answer: C
Explanation:
Understanding Schedule Performance Index (SPI):
* SPI is calculated as SPI=BCWPBCWS\text{SPI} = \frac{\text{BCWP}}{\text{BCWS}} SPI=BCWSBCWP, where BCWP is the budgeted cost of work performed, and BCWS is the budgeted cost of work scheduled.
* SPI < 1 indicates that the project is progressing slower than planned, meaning it is behind schedule.
Evaluation of Other Options:
* A: SPI > 1 would indicate the project is ahead of schedule.
* B: SPI = 1 implies the project is on schedule.
* C: Completion is not relevant to SPI.
Verification with PSP Guidelines:PSP emphasizes SPI as a key metric in earned value management (Ref:
PSP Study Guide, Chapter 1D: Earned Value Analysis).
NEW QUESTION # 55
Advice commonly purchased from consultant consists of which of the following information?
- A. Alternatives in security hardware
- B. Direction and content of security policies and procedures
- C. Number, quantity, and use of security personnel
- D. All of the above
Answer: D
NEW QUESTION # 56
Theoretically construct a summary activity for activities 2001 through 2004. Using the "normal" schedule, what is the cost of the hammock?
- A. $289,000
- B. $271,000
- C. $299,000
- D. $139,000
Answer: B
Explanation:
* Hammock Cost for Activities 2001-2004:
* Activity 2001: Cost = $150,000.
* Activity 2002: Cost = $25,000.
* Activity 2003: Cost = $20,000.
* Activity 2004: Cost = $96,000.
* Calculate Total Cost:
* Total cost = $150,000 + $25,000 + $20,000 + $96,000 = $271,000.
* Cross-Verification with Answer Options:
* Option B: Incorrect. Overstates cost.
* Option C: Incorrect. Understates cost.
* Option D: Incorrect. Overstates cost.
* Option A: Correct. Matches the calculated cost.
References:
* PSP Study Guide (2019), Section on Summary and Hammock Activities.
* AACE Recommended Practices, RP 10S-90.
NEW QUESTION # 57
The demographics of an ongoing police and security force at the ___________________ create opportunities for advancement.
- A. Advance level
- B. Management level
- C. Company Level
- D. Personal level
Answer: B
NEW QUESTION # 58
What portion of Activity B is on the critical path?
- A. First half of the activity
- B. Last half of the activity
- C. None of it
- D. The whole activity
Answer: B
Explanation:
The Critical Path comprises the sequence of activities that directly impact the project's completion time.
If only the last half of Activity B delays the subsequent activities, then this portion lies on the critical path.
References: PSP Study Guide, Section 2.4.3 - Schedule Analysis, emphasizes identifying segments of activities that are critical due to dependencies and float values.
NEW QUESTION # 59
Why does activity 11001 not show successor activities?
- A. The early finish and late finish are circular
- B. It is the penultimate work required for the project
- C. The scheduler forgot to add the successor activities
- D. It is the final activity for the required work for the project
Answer: D
Explanation:
Activity 11001 Characteristics:
* Activity 11001 (Spillway - Concrete) is logically defined as the final activity in the project.
* Final activities in a project typically do not have successor activities since they signify project completion.
Exclusion of Other Options:
* Option A: Circular logic does not apply since the scheduling logic is linear and follows standard precedence diagramming methods.
* Option B: Activity 11001 is not penultimate but the final activity.
* Option C: The scheduler's error is highly unlikely in a controlled environment following PSP principles.
Verification with PSP Guidelines:
The PSP Study Guide explains that final activities represent the culmination of a project's logical sequence and typically lack successors (Ref: PSP Study Guide, Chapter 2A: Logical Sequencing).
NEW QUESTION # 60
Employers must have a program to communicate more details on all hazards, including a ________________________ that must be available for each chemical at the work site.
- A. Procurement Asset Safety Program
- B. Asset standard Act
- C. Product stability program
- D. Material Safety Data Sheet
Answer: D
NEW QUESTION # 61
All the following describe the critical path of a schedule EXCEPT:
- A. Changed by redefining the network logic or changing activity durations or both.
- B. Frequently defined as the shortest path through the schedule.
- C. The series of activities having the least amount of total float.
- D. Determined by network logic and is the chain of activities that controls the overall project completion time.
Answer: B
Explanation:
Critical Path Characteristics:
* The critical path is the longest path through the network, defining the minimum project completion time. It cannot be the shortest path.
PSP Study Guide References:
* Critical path analysis emphasizes that it is determined by network logic and represents the chain of activities controlling the project duration.
Analysis for Selection:
* Option A, C, and D: Accurately describe the critical path.
* Option B: Incorrect; the critical path is not the shortest path.
Conclusion: The correct answer is B, as the critical path is the longest path, not the shortest.
NEW QUESTION # 62
What is a feeling of responsibility and respect that develops during an individual's formative years and is subconscious?
- A. Candor
- B. Moral honesty
- C. Trustworthiness
- D. Integrity
Answer: B
NEW QUESTION # 63
What activities are concurrent to Activity 2001 in the "normal" schedule?
- A. 2003.
- B. 1001.
- C. 1000.
- D. 7001.
Answer: B
Explanation:
* Analyze Activity 2001 in the "Normal" Schedule:
* Activity 2001 ("River Diversion Stage 1") has a duration of 92 days under the "Normal" schedule.
* The logic column shows it has a Successor ID of 2002, and a Finish-to-Start (FS) relationship with no lag. This indicates that Activity 2002 will begin immediately after Activity 2001 finishes.
* Identify Concurrent Activities Using the Schedule Logic:To determine concurrency, we need to look for activities that overlap in time with Activity 2001 during its duration. Concurrent activities must either:
* Start before Activity 2001 finishes, or
* Finish after Activity 2001 starts.
* Review Activities in the Normal Schedule:
* Activity 1001 ("Preliminary Civil Work"):
* Has a duration of 85 days, starts before Activity 2001, and overlaps with it.
* Logic: Its successor is Activity 2001 (Start-to-Start [SS] relationship), confirming the overlap.
* Activity 1000 ("General Conditions"):
* Duration is 1072 days. However, this is an overarching activity, and its inclusion is not specific to being concurrent with Activity 2001.
* Activity 7001 ("Permanent Roads"):
* Starts much later, after Activity 2001 ends, and thus is not concurrent.
* Activity 2003 ("River Diversion Dam"):
* Starts after Activity 2001 completes (FS relationship), so it is not concurrent.
* Conclusion:The only activity that overlaps and runs concurrently with Activity 2001 in the "Normal" schedule is Activity 1001.
References:
* PSP Study Guide (2019), Chapter on Schedule Development, Section 2.2.4 - Relationships: Discusses how Start-to-Start (SS) and other dependencies impact concurrency.
* AACE Recommended Practice 10S-90: "Cost Engineering Terminology" for definitions of concurrent activities.
NEW QUESTION # 64
You are developing a detailed critical path schedule for a proposed petrochemical plant. The schedule will become a part of the project baseline document, which will be sent to the company's board of directors for its consideration. What document or resource is likely to be MOST valuable in determining the schedule's work activity durations?
- A. Critical path schedules prepared by you for similar completed projects.
- B. The cost estimate for the plant prepared by your firm's estimating department.
- C. Industry publications.
- D. The Petrochemical Industry New Plant Task Duration Handbook.
Answer: A
Explanation:
Key to Duration Accuracy:
* A specialized industry handbook offers standardized and validated task durations tailored to the specific context of petrochemical plants.
Analysis of Options:
* Option A: General industry publications may lack specificity.
* Option B: Past project schedules provide insight but may not reflect the specific context or updated methodologies.
* Option C: The handbook is most relevant as it is tailored to the specific project type.
* Option D: Cost estimates are useful for budget alignment but not as precise for duration calculation.
PSP Study Guide References:
* The guide advises leveraging validated industry resources for project-specific accuracy in duration estimation.
Conclusion: The correct answer is C, as a specialized industry handbook provides the most reliable and context-specific data for duration estimation.
NEW QUESTION # 65
Why does activity 1001 have two successor activities?
- A. Because the problem could not effectively work with only one successor
- B. Because the duration of activities 2001, 2002 and 200.f require two successors
- C. Because the late finish of 1001 and the late start of 7001 require two successors
- D. Because there are two defined logic paths for the work
Answer: D
NEW QUESTION # 66
The bus transportation system, represented by the American Bus Association has established an American Action Plan designed to improve safety and safety for bus operations. The goals of this plan are all of the following EXCEPT:
- A. To promote security vigilance among operators through training and partnership with law enforcement agencies
- B. To protect the transportation infrastructure
- C. To assist companies in developing infrastructures
- D. To preserve the bus industry as a strategic transportation reserve
Answer: C
NEW QUESTION # 67
Determine the correct formula and date for the late start for Activity 9001.
- A. LF.9001 Dur.9001 -> 11-20-02.
- B. There is insufficient data provided to calculate the answer.
- C. The early finish is required in order to determine the answer.
- D. LS.6001 Dur.6001 -> 11-20-02.
Answer: A
Explanation:
* Activity Details (9001 - "Spillway - Concrete"):
* Duration: 175 days in the Normal schedule.
* To calculate Late Start (LS), the Late Finish (LF) is required. LS is calculated by subtracting the activity's duration from the LF.
* Formula for Late Start (LS):LS = LF.9001 - Dur.9001.
* Date Calculation:
* Late Finish (LF.9001) = 11-20-02 (given or derived).
* Apply the formula:LS.9001 = LF.9001 - Dur.9001= 11-20-02 - 175 days.
* Cross-Verification of Dates:
* After subtracting 175 days, LS.9001 = 11-20-02.
* Cross-Verification with Answer Options:
* Option A: Incorrect. EF (Early Finish) is not needed for this calculation.
* Option B: Incorrect. Uses LS and Dur incorrectly without connecting to LF.
* Option C: Incorrect. Data provided is sufficient.
* Option D: Correct. Matches both the formula and the date calculation.
:
PSP Study Guide (2019), Section 2A - Schedule Development, Subsection on Backward Pass Calculations.
AACE Recommended Practices, RP 10S-90, discussing Late Start and Late Finish calculations.
NEW QUESTION # 68
Using the normal schedule, given Activity 3001 and the relationship with Activity 4001. what is indicated?
- A. These activities are sequential, with Activity 4001 starting 15 days earlier than the start of Activity
3001. - B. These activities are partially concurrent, with Activity 4001 starting 15 days after the start of Activity 3001
- C. The activities are independent, with Activity 4001 starting 15 days earlier than the start of Activity 5001
Answer: B
Explanation:
Relationship Analysis:
* Activity 4001 starts 15 days after Activity 3001 begins, based on their logical dependency (SS +15).
* This indicates partial concurrency, as both activities overlap in execution.
Evaluation of Other Options:
* A: Incorrect, as the statement refers to Activity 5001, not 3001.
* C: Incorrect, as Activity 4001 does not start before Activity 3001.
Verification with PSP Guidelines:PSP guidelines stress precise interpretation of activity relationships (Ref:
PSP Study Guide, Chapter 2A: Logical Relationships and Lags).
NEW QUESTION # 69
Using the normal schedule, what is the owner's total cost of the project?
- A. S13.102.900
- B. S12.990.000
- C. S12.953.600
- D. S13.990.600
Answer: C
NEW QUESTION # 70
Security services in which the security force is hired and controlled directly by the protected organization are called:
- A. Security enforcement
- B. Contract security services
- C. Proprietary
- D. Pilferage
Answer: C
NEW QUESTION # 71
A study of BDP international has found that ___________ of shippers are factoring in additional time to comply with the Advanced Manifest System, which went into effect in February 2003. This Department of Homeland security rule requires the filing of complete import manifest documentation at least 24 hours before
U.S.-bound ships are loaded at foreign ports.
- A. 35 percent
- B. 30 percent
- C. 25 perc
- D. 40 percent
Answer: B
NEW QUESTION # 72
......
ASIS PSP (ASIS Physical Security Professional) certification exam is an industry-standard examination for professionals who are pursuing a career in physical security. PSP exam is designed to test a candidate's knowledge and skills in various domains of physical security, including threat assessment, risk analysis, security planning, and implementation. ASIS Physical Security Professional Exam certification is internationally recognized and signifies a professional's competence and expertise in the field of physical security.